A road widening project forced a DN315 PE medium-pressure gas line to move 9 meters. Rather than purge and re-commission the section, the contractor stopped the line live at both ends and tied in the new run.
Medium-pressure PE is unforgiving: any weld you cut out has to be proven again, and a purge on a live distribution network means telling thousands of customers to expect an outage.
The contractor set two line stop tees, one upstream and one downstream of the section to be relocated. Each was hot tapped through a sandwich valve, and a plug head was inserted to seal the pipe. With the section isolated, it was cut, the new 9-meter run was fused in place, and the heads were retracted after pressure testing.
Total isolation time was under seven hours, all of it inside a night permit. No customer meter saw a pressure drop. The same crew has since used the equipment on four more road projects in the city.