Projects where shutting down was not an option.
2025A chemical tanker's ballast system was upgraded to 316L during a nine-day dry-docking. Cutting, beveling and fitting had to happen in a confined space with no hot work permit.
Read the case →
2024A new industrial park needed a 600 mm branch off the transmission main. Shutting the main meant cutting water to 12,000 households. We tapped it live, between 23:00 and 05:00, with a hydraulic machine and a mechanical tapping saddle.
Read the case →
2024A road widening project forced a DN315 PE medium-pressure gas line to move 9 meters. Rather than purge and re-commission the section, the contractor stopped the line live at both ends and tied in the new run.
Read the case →
2024A 400 mm cast iron heating main under a tram line had three pinhole leaks. Excavation meant closing the street for a week. Two repair clamps and one night of work solved it.
Read the case →
2023Six branch connections had to be added to a 24-inch cooling water header while the refinery kept running. Every item was pre-assembled and pressure-tested before the window opened.
Read the case →
2023A 20-inch tailings line at 3,800 meters needed a failed knife gate valve replaced. Draining the line would have stopped the concentrator for two days.
Read the case →Send the diameter, working pressure and what flows inside. We reply with a specification and price within one working day.