Six branch connections had to be added to a 24-inch cooling water header while the refinery kept running. Every item was pre-assembled and pressure-tested before the window opened.
Turnarounds are won or lost on preparation. The contractor had a fixed 36-hour window and six connections to make, spread across a header that could not be fully drained because two process units stayed online.
We supplied ANSI Class 150 tapping saddles, sandwich valves and a hydraulic machine with a split-frame cutter sized for 24-inch carbon steel. Flange dimensions, gasket and bolt grades were checked against the client's piping spec before shipment, and every assembly was hydro-tested at 1.5 times design pressure in our workshop.
On site the six outlets were cut in sequence, each in under 20 minutes. Because the saddles arrived pre-assembled with the valves, no field fitting was needed. The header was back in service four hours ahead of the window closing.
Send the diameter, working pressure and what flows inside. We reply with a specification and price within one working day.