← All projects Mining · Chile · 2023

Tailings line valve replaced at altitude, on a live line

A 20-inch tailings line at 3,800 meters needed a failed knife gate valve replaced. Draining the line would have stopped the concentrator for two days.

Slurry lines are abrasive and the valves take the worst of it. This knife gate had eroded to the point where it would no longer isolate, so the whole line had to be treated as live.

We supplied a 20-inch line stop system: two stop tees with sandwich valves, hydraulic cylinders and completion plugs. The heads were inserted either side of the valve, the cavity was drained, the old valve unbolted and the replacement fitted on the same flange faces.

The work took 11 hours including the drain and re-pressurization. The concentrator never stopped. Spare heads were left on site so the mine can repeat the procedure without waiting for a shipment.

0 hconcentrator downtime
11 htotal job
3,800 maltitude

Tell us the pipe, pressure and medium

Send the diameter, working pressure and what flows inside. We reply with a specification and price within one working day.

Send an inquiry →
WeChat Scan to add on WeChat JC-Leon
+86 18130056225